To view your task without having date constraints
Step 1
To view your completion date from its starting / ending without having date constraints such as holidays from affecting it, first you need to go to Project and select Task Information.
Step 2
Then a new window will appear as illustrated below. Under the Advance tab choose Constrain Type.
Step 3
Later, you need to choose As Soon As Possible if you want to measure your project from its starting date or Choose As Late as Possible if you wanted to measure your project from its ending date.