To set Priority

Step 1

To setup the priority for a task, switch to Gantt chart, and then double click on your task. Under the general tab, choose Priority and then set it to a value for example "750". The maximum number for priority is 1000.

What can a resource graph do for me?

A resource graph gives a graphical view of the allocation of resources of whether the allocation of resources is over allocated or not. Therefore we can perform adjustment to our resources to cater for the maladjustment done by us.

Step 1

First you need to go to View and then choose the Resource Graph. An example of resource graph is illustrated below.