Friday, November 30, 2007

How to calculate Overtime Cost

How to calculate Overtime Cost

To calculate Overtime Cost

Step 1

To calculate a cost for this project, we need to go to Task Usage. And then we will add a new Cost column so that we will be able to see the cost of a project.

Step 2

To add a new column, right click on our Duration column and then when the popup menu is up, choose Insert Column.

Step 3

Another window will appear as shown below.

Step 4

Under the field name, we need to choose Cost and then click Ok when you have done.

Step 5

Then, we are able to view our cost as shown below.

No comments: