How to set up different cost on a different date

How to set up different cost on a different date

To set up different cost on a different date

Step 1

To setup cost for a significant date, this is what we can do. First you need to go to Resource Sheet and then double click on our resources. Next, you need to double click on System Analyst and this is where we are going to set our charges differently.

Step 2

Next, you need to set the effective date to Friday 22 March 2002 and the rate will be $100. After that, just click on Ok.